Question: Given the estimated activity times and the network below: START END Activity a (optimistic m (most time) likely time) b (pessimistic time) . A 3

Given the estimated activity times and theGiven the estimated activity times and the

Given the estimated activity times and the network below: START END Activity a (optimistic m (most time) likely time) b (pessimistic time) . A 3 10 11 B 8 10 18 C 2 3 4 D 6 7 8 E 1 6 17 F 5 7 9 G 4 6 8 8 I . 5 8 00 17 Expected Activity a mb Variance Time A 3 10 11 9 1.78 B 8 10 18 2.78 IC C 2 3 4 3 D 6 7 8 7 0.11 E 1 6 17 7.11 F 5 7 9 7 0.44 G 4 6 8 0.44 H 5 8 17 4.00