Question: Given the flowing project network, baseline, and status information, develop status reports for periods 1 through 6. A. Compute the SV, CV, SPI, and CPI
Given the flowing project network, baseline, and status information, develop status reports for periods 1 through 6.
A. Compute the SV, CV, SPI, and CPI for periods 2, 4, 6, 8, 10, and 12.
B. Complete the SPI, CPI, and PCIB in the index table.
C. Plot the EV and the AC on the summary graph provided. (You may use your own graphs.)
D. What is your assessment of the project at the end of period 12?