Question: Given the follow production line: Task a (2 min)------------>Task b (4 min)------------>Task c (3 min)------------>Task d (2 min) What is the cycle time? Group of
Given the follow production line: Task a (2 min)------------>Task b (4 min)------------>Task c (3 min)------------>Task d (2 min) What is the cycle time? Group of answer choices 2 minutes 4 minutes 3 minutes 11 minutes