Question: Given the Following Activities for a Website Design Draw a Project Network and Determine the Critical Path ( Show complete diagram ) Determine the one
Given the Following Activities for a Website Design
Draw a Project Network and Determine the Critical Path Show complete diagram
Determine the one best activity to crash by adding more labor to complete the website in days. Show complete crashed project network diagram
How many days can they delay information gathering until it lengthens the overall completion time for the website?
tableActivityDescription,tableImmediatePredecessorTime DaystableInformationGatheringPlanning,CDesign,BDtableContentWritingandAssemblysmmmCoding,CDFtableWebsiteTestingEGtableWebsiteReviewELaunch,