Question: Given the following activity network: A2 A A1 Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 2 weeks. What is the

Given the following activity network: A2 A A1
Given the following activity network: A2 A A1 Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 2 weeks. What is the earliest completion time of A3? 13 weeks 15 weeks 10 weeks 7 weeks