Question: Given the following activity network: Activity A1 takes 3 weeks, A2 takes 8 weeks, A3 takes 6 weeks, A4 takes 9 weeks, A5 takes 4

Given the following activity network: Activity A1

Given the following activity network: Activity A1 takes 3 weeks, A2 takes 8 weeks, A3 takes 6 weeks, A4 takes 9 weeks, A5 takes 4 weeks. What is the slack time of A3? weeks (round to the nearest integer)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts