Question: Given the following activity network: The figure shows a possible branching. A 1 , leads to A 2 and A 3 . Activity A 1

Given the following activity network:
The figure shows a possible branching. A1, leads to A2 and A3.
Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 2 weeks. What is the slack time for A1?
Multiple Choice
8
2
5
0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!