Question: Given the following activity summary, what is the planned duration (in days) of the entire project? ACTIVITY IMMEDIAT PREDECESSO DAYS A 7 B B 2

Given the following activity summary, what is the

Given the following activity summary, what is the planned duration (in days) of the entire project? ACTIVITY IMMEDIAT PREDECESSO DAYS A 7 B B 2 3 A D 5 A E 7 B F 3 G 4 D H 6 E, F 1 5 G H