Question: Given the following cost loaded baseline schedule and progress report at week 3, how much is your project projected to be over or under budget

Given the following cost loaded baseline schedule and progress report at week 3, how much is your project projected to be over or under budget at completion (use a negative number for under budget, a positive number for over budget)? Your actual cost of work performed is $19,240. Round your answer to the nearest whole number. COST-LOADED BASELINE SCHEDULE Budgeted Cost % Complete Week 1 Week 2 Week 3 Week 4 Week 5 Task A $ 10,678 91 Task B $ 1,611 100 Task C $ 2,666 60 Task D $ 859 75 Task E $ 5,344 98 Task F $ 3,429 40