Question: Given the following data about a project: the TBC = $226,000, the CEV = $162,000, the CAC = $126,000. Calculate CPI. Interpret CPI. Calculate FCAC
-
-
Given the following data about a project: the TBC = $226,000, the CEV = $162,000, the CAC = $126,000.
Calculate CPI. Interpret CPI. Calculate FCAC using the first method discussed in the textbook. Interpret FCAC.
-
Given the following data about a project: the TBC = $362,000, the CEV = $226,000, the CAC = $222,000.
Calculate CPI. Interpret CPI. Calculate FCAC using the second method discussed in the textbook. Interpret FCAC.
-
What is the CV for a project that has a TBC = $526,000, a CEV = $226,000, a CAC = $222,000, and CBC = $226,000? Interpret the value of CV. Calculate TCPI. Interpret the TCPI value.
-
What is the CV for a project that has a TBC = $662,000, a CEV = $366,000, a CAC = $322,000, and CBC = $322,000? Interpret the value of CV. Calculate TCPI. Interpret the TCPI value.
-