Question: Given the following data: Actual units produced: 15,000 Actual variable overhead incurred: $49,800 Actual machine hours worked: 15,000 Standard variable overhead cost per machine hour:
Given the following data:
Actual units produced: 15,000
Actual variable overhead incurred: $49,800
Actual machine hours worked: 15,000
Standard variable overhead cost per machine hour: $3.40
ifoverhead is applied based onmachine hours and it is estimated to take1.10 machine hours to manufacture a unit, the variable overhead efficiency variance is:
- $1,200 favorable.
- $1,200 unfavorable.
- $5,100 favorable.
- $5,100 unfavorable.
- None of the answers is correct.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
