Question: Given the following data below, find: Normal Crash Activitiy Time (days) Cost Time (days) Cost 1,2 6 50 4 80 1,3 5 80 3

Given the following data below, find: Normal Crash Activitiy Time (days) Cost

Given the following data below, find: Normal Crash Activitiy Time (days) Cost Time (days) Cost 1,2 6 50 4 80 1,3 5 80 3 150 2,4 5 60 2 90 2,5 B 100 6 3:00 3,4 5 140 2 200 4,5 3 60 1 80 490 1. The network diagram 2. Number of Paths (Durations for each path) 3. Critical Path (Duration) 4. Reduce the project to 10 days. Calculate the final cost. Now, what is the Critical Path