Question: Given the following data for a project network: Events (nodes) Times (weeks) Activity Start Finish Optimistic Most Likely Pessimistic A1 29 15 21 B1313 21

Given the following data for a project network:

Given the following data for a project network: Events (nodes) Times (weeks) Activity Start Finish Optimistic Most Likely Pessimistic A1 29 15 21 B1313 21 23 C246 918 D 25 23 35 47 E 35 19 26 27 F46 23 29 41 G 56 14 20 26 H6 72 5 8 What is the estimated expected mean time (in weeks) for activity A? Use formula. O 10 15 20 25