Question: Given the following data for Crane Company, compute (A) total manufacturing costs and (B) costs of goods manufactured: Direct materials used $210000 Beginning work in
Given the following data for Crane Company, compute (A) total manufacturing costs and (B) costs of goods manufactured:
| Direct materials used | $210000 | Beginning work in process | $40000 | |
|---|---|---|---|---|
| Direct labor | 140000 | Ending work in process | 20000 | |
| Manufacturing overhead | 190000 | Beginning finished goods | 50000 | |
| Operating expenses | 290000 | Ending finished goods | 30000 |
| (A) | (B) |
| $520000 | $560000 |
| $540000 | $520000 |
| $540000 | $560000 |
| $560000 | $580000 |