Question: Given the following data for Project M, calculate the NPV of the project. year1. year 2. year 3 cash flow in real terms. -200 150

Given the following data for Project M, calculate the NPV of the project.

year1. year 2. year 3

cash flow in real terms. -200 150 120

real discount rate = 5%

nominal disc. rate = 10%