Question: Given the following data for Project M calculate the NPV of the project. C0 C1 C2 Cash flow in nominal terms: 100 75 60 Real
Given the following data for Project M calculate the NPV of the project.
| C0 | C1 | C2 | |
| Cash flow in nominal terms: | −100 | 75 | 60 |
| Real discount rate = 5% | |||
| Inflation rate = 4% |
- Calculate the discount rate assuming there is no risk.
- Calculate the NPV of this project applying the discount rate calculated in above question.
Step by Step Solution
3.37 Rating (169 Votes )
There are 3 Steps involved in it
To calculate the discount rate assuming there is no risk we can use the nominal interest rate as a p... View full answer