Question: Given the following data, how many kitchen sinks would be ordered to satisfy gross requirements? Item: Kitchen Sink Lead Time = 2 week Lot size
Given the following data, how many kitchen sinks would be ordered to satisfy gross requirements?
| Item: Kitchen Sink | Lead Time = 2 week | |||
| Lot size rule: FOQ = 25 | Beginning Inventory = 2 | |||
| Period | 1 | 2 | 3 | 4 |
|---|---|---|---|---|
| Gross Requirements | 0 | 0 | 5 | 6 |
9
11
25
50