Question: Given the following data / information, determine the elevation of the weir crest at the river (8 marks): Ground level at head of scheme =

Given the following data / information, determine the elevation of the weir crest at the river (8 marks):

  • Ground level at head of scheme = 2000 m amsl;
  • Operation head = 0.50 m
  • Canal length to head works = 5.0 km
  • Slope of the canal = 0.5%
  • Head loss across structures = 1.50m
  • Head loss at intake = 0.10m

If the weir height is 1.0m, what is the river bed level at the head works?

Step by Step Solution

3.48 Rating (151 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The detailed answer for the above question is provided below Head of scheme 20000 WL hea... View full answer