Question: Given the following data, use present worth analysis to find the best alternative, A , B , or C . Use 1 5 % interest.

Given the following data, use present worth analysis to find the best alternative, A, B, or C. Use 15% interest.
A
B
C
Initial cost
$10,000
$15,000
$12,000
Annual benefit
6,000
10,000
5,000
Salvage value
1,000
-2,000
3,000
Useful life
2 years
3 years
4 years
Question 1Answer
a.
NPW A: $1702; NPW B: $15,473; NPW C: $7576. Recommendation: Alternative B
b.
NPW A: $1702; NPW B: $21,717; NPW C: $7576. Recommendation: Alternative B
c.
NPW A: -$3341; NPW B: $21,717; NPW C: $1063. Recommendation: Alternative B
d.
NPW A: $3767; NPW B: $34,253; NPW C: $16,771. Recommendation: Alternative B

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!