Question: Given the following information, a) Draw the activity on node (AON) diagram b) Find the critical path of the project. Then, calculate the total duration

Given the following information,

a) Draw the activity on node (AON) diagram

b) Find the critical path of the project. Then, calculate the total duration of the critical path.

c) Find the total float and free float for each activity

Activity Pred. Duration
A - 3
B A 3
C A 5
D A 7
E B 6
F B 7
G B,C 6
H D 9
I D,E,F,G 8