Question: Given the following information about a project: List ALL Activities that are on the Critical Path Task Early Start(DAYS Latest Start(DAYS) A 10 16 B
Given the following information about a project: List ALL Activities that are on the Critical Path
| Task | Early Start(DAYS | Latest Start(DAYS) |
|
| A | 10 | 16 |
|
| B | 8 | 10 |
|
| C | 14 | 20 |
|
| D | 16 | 18 |
|
| E | 24 | 26 |
|
| F | 16 | 24 |
|
| G | 28 | 30 |
|