Question: Given the following information and MRP table for part A; The net requirement in week 6 will be: 1-There will be a previously arranged scheduled
Given the following information and MRP table for part A; The net requirement in week 6 will be:
1-There will be a previously arranged scheduled receipt of 400 units of part A at the beginning of week 2. 2- Manufacturing lead time is two weeks. 3- This part must be ordered in multiples of 100 units. 4-Currently, there are 700 on-hand inventory. Parts/ Week 1 2 3 4 5 6 Part: A Lt=2 week Lot size: Q=100 Projected on hand= 700 Open order in week 2= 400 Gross Requirements 500 320 540 610 800 920 Scheduled receipts 400 Projected on-hand 700 Net requirements Planned-order receipts Planned-order releases Multiple Choice 890 600 800 300 900