Question: Given the following information and MRP table for part D; The planned order release in week 3 will be: 1 - Currently, there are 2

Given the following information and MRP table for part D; The planned order release in week 3 will be:1-Currently, there are 240 on-hand inventory.2-There will be a previously arranged scheduled receipt of 600 units of part D at the beginning of week 6.3- Lot-for-lot ordering is used.4- Lead time is one week.Part/ Weeks1234567Part: D1week Lot size:GrossRequirements120180300300360560240L4L Projected on hand=240Scheduled receipts600Open order in week 6=600Projected on-hand240Net requirementsPlanned-order receiptsPlanned-order releases