Question: Given the following information and MRP table for part E; The net requirement in week 3 will be: 1-Currently, there are 120 on-hand inventory.

Given the following information and MRP table for part E; The net requirement in week 3 will be: 1-Currently, there are 120 on-hand inventory. 2-There will be a previously arranged scheduled receipt of 300 units of part E at the beginning of week 3. 3- This part must be ordered in multiples of 100 units. 4- Lead time is one week. Part/ Week Part: E Lt=1 week Lot size: Q=100 Projected on hand= 120 Open order in week Net requirements 3= 300 000 340 120 280 Gross Requirements Scheduled receipts Projected on-hand 0 260 Planned-order receipts Planned-order releases 1 2 3 4 5 6 7 100 280 340 500 380 720 200 300 120
Step by Step Solution
3.47 Rating (147 Votes )
There are 3 Steps involved in it
We created an MRP table using the information provided in the questio... View full answer
Get step-by-step solutions from verified subject matter experts
