Given the following information, complete the planned order releases and projected on-hand balances for component part A.
Fantastic news! We've Found the answer you've been seeking!
Question:
- Given the following information, complete the planned order releases and projected on-hand balances for component part A.
Part A | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | |
Gross Requirements | 90 | 0 | 85 | 0 | 100 | |
Scheduled Receipts | 60 | 0 | 0 | 0 | 0 | |
Projected Balance | 130 | 100 | 100 | 15 | 65 | 15 |
Planned Order Releases | 50 | 50 | 0 | 0 | 0 | |
Q = 50, LT = 3 weeks, Safety Stock = 10