Question: Given the following information, construct a time- phased budget for your project. (All cost figures are in $000s). What are weekly planned and cumulative costs

Given the following information, construct a time- phased budget for your project.
(All cost figures are in $000s). What are weekly planned and cumulative costs for phased budget for your project.
Table for Problem 8.20
Work Package Budget Week 1 Week 2 Week 3 Week 4 Week 5
Staffing 9 7 2
Blueprinting 16 4 10 2
Prototyping 17 2 10 4 1
Full Design 30 4 12 14
Plan
Cumulative