Question: Given the following information, construct a time- phased budget for your project. (All cost figures are in $000s). What are weekly planned and cumulative costs
Given the following information, construct a time- phased budget for your project. (All cost figures are in $000s). What are weekly planned and cumulative costs for phased budget for your project. Table for Problem 8.20 Work Package Budget Week 1 Week 2 Week 3 Week 4 Week 5 Staffing 9 7 2 Blueprinting 16 4 10 2 Prototyping 17 2 10 4 1 Full Design 30 4 12 14 Plan Cumulative
Step by Step Solution
There are 3 Steps involved in it