Question: Given the following information, create a Gantt chart for this project: (hint: for activity 2, you have to finish activity 1 before you can start

  1. Given the following information, create a Gantt chart for this project: (hint: for activity 2, you have to finish activity 1 before you can start 2)

Given the following information, create a Gantt

activity time precedence 1 2 2 1 4 WN 3 2 3 w WNA ANWAN N 3 2 4 4 5 64,5 7 2 6 3 00 6 4