Question: Given the following information, determine the activity rate for setups. Activity Pool Activity Base Budgeted Amount Setups 10,500 $50,900 Inspections 25,200 $147,300 Assembly (DLH) 71,200
Given the following information, determine the activity rate for setups.
| Activity Pool | Activity Base | Budgeted Amount |
| Setups | 10,500 | $50,900 |
| Inspections | 25,200 | $147,300 |
| Assembly (DLH) | 71,200 | $378,500 |