Question: Given the following information, determine the activity rate for setups. Activity Pool Activity Base Budgeted Amount Setups 10,500 $50,900 Inspections 25,200 $147,300 Assembly (DLH) 71,200

Given the following information, determine the activity rate for setups.

Activity Pool Activity Base Budgeted Amount
Setups 10,500 $50,900
Inspections 25,200 $147,300
Assembly (DLH) 71,200 $378,500