Question: Given the following information for a one - year project, answer the following questions. Recall that PV is planned value, EV is earned value, AC

Given the following information for a one-year project, answer the following questions. Recall that PV is planned value, EV is earned value, AC is the actual cost, and BAC is the budget at completion.
PV = $22,000
EV = $20,000
AC = $25,000
BAC = $120,000
What is the cost variance, schedule variance, cost performance index, and schedule performance index for the project? (1 point)
How is the project going? Is it ahead of schedule or behind schedule? Is it under budget or over budget? (1 point)
Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? (1 point)
Use the CPI to calculate how long it will take to finish this project. (1 point)
Sketch the earned value chart for this project, using Figure 7-6 from the text as a guide. (1 point)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!