Question: Given the following information for a one - year project, answer the following questions. Recall that PV is planned value, EV is earned value, AC
Given the following information for a oneyear project, answer the following questions. Recall that PV is planned value, EV is earned value, AC is the actual cost, and BAC is the budget at completion.
PV $
EV $
AC $
BAC $
What is the cost variance, schedule variance, cost performance index, and schedule performance index for the project? point
How is the project going? Is it ahead of schedule or behind schedule? Is it under budget or over budget? point
Use the CPI to calculate the estimate at completion EAC for this project. Is the project performing better or worse than planned? point
Use the CPI to calculate how long it will take to finish this project. point
Sketch the earned value chart for this project, using Figure from the text as a guide. point
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock