Question: Given the following information for a one year project, address the following queries: Planned Value PV = $23000 Earned Value EV = $20000 Actual cost
Given the following information for a one year project, address the following queries:
Planned Value PV = $23000
Earned Value EV = $20000
Actual cost AC = $25000
Budget at completion BAC = $120000
Formulas are given below. Hint: Chapter 7, Page 312 to 316 of your ref book (IT Project Management by kathy).
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock