Question: Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC
- Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion.
PV = $22,000
EV = $20,000
AC = $25,000
BAC = $120,000
Sketch the earned value chart for this project, using the picture below as a guide.

Estimate at completion (EAC) 120,000 Budget at completion (BAC), 100,000 An EAC point above and to the right of the BAC point means the project is projected to cost more and take longer than planned 80,000 Planned value (PV) $ 60,000 40,000 | Actual cost (AC). Earned value (EV) 20,000 - N- TI 1 2 3 4 5 6 7 Month 8 9 10 11 12 13 ---- Actual cost (AC) Planned value (PV) --- Earned value (EV)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
