Question: Given the following information for a one-year training project, answer the following questions. Recall that PV is the planned value, EV is the earned value,

Given the following information for a one-year

Given the following information for a one-year

Given the following information for a one-year training project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = R20,000 EV = R20,000 AC = R20,000 BAC= R1,000,000 4.1 What is the total cost per month for each of the WBS categories? 4.2 What is the total cost per year for each of the WBS categories? 4.3 What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? 4.4 How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? 4.5 Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? 4.6 Use the Spl to estimate how long it will take to finish this project. 4.7 Sketch the earned value chart for this project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!