Question: Given the following information for a project, what are the estimated slack times ( in days ) for activities A - H ? table

Given the following information for a project, what are the estimated slack times (in days) for activities A-H?
\table[[Activity,\table[[Immediate],[Processor]],Activity Time],[(days),,],[A,-,6],[B,-,8],[C,A, B,5],[D,B,4],[E,C,7],[F,C, D,3],[G,D,6],[H,E, F, G,5]]
)=0;B=0;C=0;D=2;E=0;F=4;G=2;H=(0)=2;B=0;C=0;D=2;E=0;F=4;G=2;H=(0)=3;B=0;C=1;D=2;E=0;F=4;G=2;H=(0)=4;B=0;C=0;D=3;E=0;F=4;G=2;H=(0
None of the above