Question: Given the following information: Job Arrival Time CPU Cycle A 0 10 B 2 4 C 3 25 D 6 15 E 9 4 Calculate

Given the following information: Job Arrival Time CPU Cycle A 0 10 B 2 4 C 3 25 D 6 15 E 9 4 Calculate the start time, and finish time for each of the five jobs using the following. Make sure you draw the time line: 1- FCFS 2- SJN 3- SRT 4- Round Robin (Time quantum=5)