Question: Given the following information on a research project: m Activity Immediate Estimate Activity Activity Activity Manpower Predecessors Times (Days) Expected Variance a Time (te) A

Given the following information on a research

Given the following information on a research project: m Activity Immediate Estimate Activity Activity Activity Manpower Predecessors Times (Days) Expected Variance a Time (te) A 3 5 7 a a) 4 B 1 3 5 b (6) 3 AB 5 7 9 D B 4 6 8 (d) 5 E C D 2 4 6 e) e) 5 F E 2 3 4 (1) (f) 2 G DF 3 4 5 1 Draw the Gantt chart based on the earliest start time (ES-EF) for each activity. * Upload your solution for this