Question: Given the following information, prepare the MPS using a Fixed Order Quantity (FOQ) of 60 and calculate the projected available inventory balances. What is the
Given the following information, prepare the MPS using a Fixed Order Quantity (FOQ) of 60 and calculate the projected available inventory balances. What is the projected available inventory balance at the end of period 2?

Safety Stock = 20 1 60 2 70 3 50 Periods 4 35 5 45 6 45 20 Forecast Projected Available Balance (Inventory) Master Production Schedule Moving to another question will save this response. Question 27 of 34 MART 20 62 21 S A all