Question: Given the following information, the forecast for period two using exponential smoothing and a = 0 . 4 is 6 7 Period Demand Forecast 1

Given the following information, the forecast for period two using exponential smoothing and a =0.4 is 67 Period Demand Forecast 16459270 Select one True Or False