Given the following information with demand and performance cycle certainty:
Average daily demand =15 units
Performance cycle =5 days
Order quantity (from (EOQ)=150 units
Review period =2 weeks (10 working days)
Calculate:
a) the reorder point utilizing the perpetual review method
b) the reorder point utilizing the periodic review method