Question: Given the following initial inventory, forecast and order quantities for an item. The MPS or the lot size is 100 because of the production run.
- Given the following initial inventory, forecast and order quantities for an item. The MPS or the lot size is 100 because of the production run. Production rule is to schedule when the projected on- hand is less than 10. Use the worksheet on the next page to answer the question. (10 pts.)
- Projected Ending inventory
- Availabletopromise inventory (ATP).
| On- hand/Beginning Inventory 60 | June | July | ||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
| Forecast | 60 | 85 | 110 | 90 | 120 | 45 | 55 | 80 |
| Booked Orders(com mitted) |
70 |
60 |
35 |
20 |
|
|
|
|
| Requirements=
Max (F, OB) |
|
|
|
|
|
|
|
|
|
Projected Ending Inventory |
|
|
|
|
|
|
|
|
| MPS |
|
|
|
|
|
|
|
|
| AvailableTo Promising Inventory (ATP) |
|
|
|
|
|
|
|
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts