Question: Given the following Master Schedule Data: Calculate the Projected Ending Inventory for week 18: Ending Inventory EI, = E1,-, +MPS, - max(F,,OB) where El= ending

Given the following Master Schedule Data:

Given the following Master Schedule Data: Calculate the Projected Ending Inventory for week 18: Ending Inventory EI, = E1,-, +MPS, - max(F,,OB) where El= ending inventory in time period MPS, master production schedule quantity available in time period 1 F - forecasted demand for time period OB, - orders booked for time period Week 16 17 Forecasted Demand 18 40 40 Booked Orders 30 50 Master Production Schedule (Planned Production) Projected Ending Inventory 60 60 30 O A 40 OB. 20 Oco OD 50