Question: Given the following MRP matrix for Item E: ITEM: E Lot Size: L4L LT: 3 Period 1 2 3 4 5 6 7 Gross Requirements

Given the following MRP matrix for Item E: ITEM: E Lot Size: L4L LT: 3 Period 1 2 3 4 5 6 7 Gross Requirements 200 100 200 200 300 200 300 Schedule Receipts 300 Project on Hand 500 Net Requirements Planned Order Receipts Planned Order Releases The planned order releases for period 4 would be

Select one: A. 200 B. 0 C. 300 D. 75