Question: Given the following network, D7 A8 G5 Start -E6 c E6 End B10 F7 (a) What is the critical path? (b) How long will it

Given the following network, D7 A8 G5 Start -E6 c
Given the following network, D7 A8 G5 Start -E6 c E6 End B10 F7 (a) What is the critical path? (b) How long will it take to complete this project? (c) Can activity B be delayed without delaying the completion of the project? If so, how many days