Question: Given the following network diagram for a project, determine each of the following ( activity times are in weeks ) : a ) Identify all
Given the following network diagram for a project, determine each of the following activity times are in weeks:
a Identify all paths in the network.
b Determine each path's length.
c Identify the Critical Paths
d Calculate the expected project duration.
Question a and b
Use the information you have calculated on the worksheet to answer c and d
Question c
The critical path is
Question d
The project duration is weeks.
Given the following network diagram for a project, determine each of the following activity times are in weeks:
a Identify all paths in the network.
b Determine each path's length.
c Identify the Critical Paths
d Calculate the expected project duration.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock