Question: Given the following network with activity times in weeks, determine the earliest start and finish times, latest start and finish times, and slack for each
Given the following network with activity times in weeks, determine the earliest start and finish times, latest start and finish times, and slack for each
activity. Calculate the project duration and indicate the critical path.
a What is the slack of activities A and K When is the last moment activity C must finish? When is the last moment activity G must start?
b What would happen if activity F would take weeks rather than And what if F took weeks rather than
c What would you do to reduce the project duration by weeks? Explain.
Start End
A
B
C
D
E
J
F
G
H
I
L
K
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
