Question: Given the following network with activity times in weeks, determine the earliest start and finish times, latest start and finish times, and slack for each

Given the following network with activity times in weeks, determine the earliest start and finish times, latest start and finish times, and slack for each
activity. Calculate the project duration and indicate the critical path.
a) What is the slack of activities A and K? When is the last moment activity C must finish? When is the last moment activity G must start?
b) What would happen if activity F would take 3 weeks rather than 6? And what if F took 8 weeks rather than 6?
c) What would you do to reduce the project duration by 2 weeks? Explain.
Start End
A3
B7
C5
D4
E8
J8
F6
G14
H4
I7
L2
K3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!