Question: Given the following partially completed Project Activity Description and Network Diagram, calculate the SLACK for ACTIVITY E. Activity Duration Predecessor| ES | EF LF SLACK

Given the following partially completed Project
Given the following partially completed Project Activity Description and Network Diagram, calculate the SLACK for ACTIVITY E. Activity Duration Predecessor| ES | EF LF SLACK A 2 - 0 20 20 B10 | 2 12 2 120 C 8 A 2 10 6 14 7 12 1912 19 0 B, C 12 17 5 D, E 4 D E 17 21 UU 001 19 B, 10 D, 7 F, 5 19 START FINISH 1721 C, 8 E, 5