Question: Given the following process/resource information, construct a resource-allocation graph and a wait-for graph. Is deadlock possible? Explain. Resource # of instances Requested by Allocated to

Given the following process/resource information, construct a resource-allocation graph and a wait-for graph. Is deadlock possible? Explain. Resource # of instances Requested by Allocated to R1 2 P3 P1, P2 R2 1 P4 P3 R3 2 P4 P2, P3 R4 1 P1 P2