Question: Given the following product tree, explode, offset, and determine the gross and net requirements. All lead times are one week, and the quantities required are

Given the following product tree, explode, offset, and determine the gross and net requirements. All lead times are one week, and the quantities required are shown in parentheses. The customer calls for 500 As to be available in week 5. The BOM tree structure is: it needs 2 Bs and 2 Cs to make an A; 2 Ds and 1 E to make a B, and 1 D and 2 Fs to make a C. Then, the Planned Order Release of part E in period 2 is:

A

B

2

C

2

D

E

D

F

2

1

1

2

Part

Week

1

2

3

4

5

A

Gross Requirements

Projected Available

Net Requirements

Planned Order Receipt

Planned Order Release

B

Gross Requirements

Projected Available

Net Requirements

Planned Order Receipt

Planned Order Release

C

Gross Requirements

Projected Available

Net Requirements

Planned Order Receipt

Planned Order Release

D

Gross Requirements

Projected Available

Net Requirements

Planned Order Receipt

Planned Order Release

E

Gross Requirements

Projected Available

Net Requirements

Planned Order Receipt

Planned Order Release

F

Gross Requirements

Projected Available

Net Requirements

Planned Order Receipt

Planned Order Release

Select one:

a. 3000

b. 1000

c. 2000

d. None of them

e. 500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!