Question: Given the following production plan, use a ( a ) chase production strategy and ( b ) level production strategy to compute the monthly production,

Given the following production plan, use a (a) chase production strategy and (b) level production strategy to compute the monthly production, ending inventory/backlog, and workforce levels. A worker can produce 100 units per month. Assume beginning inventory as of January is 0, and the firm desires to have zero inventory at the end of June.
Month Jan. Feb. Mar. Apr. May Jun.
Demand 200030005000600060002000
Production
Ending Inventory
Workforce
In a chase production strategy, what is the ending inventory/backlog in June?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!