Question: Given the following production plan, use a ( a ) chase production strategy and ( b ) level production strategy to compute the monthly production,

Given the following production plan, use a (a) chase production strategy and (b) level production strategy to compute the monthly production, ending inventory/(backlog), and workforce levels. A worker can produce 100 units per month. Assume the beginning inventory as of January is 0, and the firm desires to have zero inventory at the end of June.
MONTH JAN FEB MAR APR MAY JUN
Demand 2,0003,0005,0006,0006,0002,000
Production
Ending Inventory
Workforce