Question: Given the following production schedule, compute the available-to-promise quantities. Table 4 Week 1 2 3 4 5 6 7 8 Model B MPS BI =
-
Given the following production schedule, compute the available-to-promise quantities.
Table 4
Week
1
2
3
4
5
6
7
8
Model B
MPS
BI = 30
20
0
20
20
0
20
20
20
Committed Customer Orders
10
10
10
10
10
0
0
10
ATP:D
What is ATP in week 1?
A. 20
B. 30
C. 40
D. 50
-
Based on Table 4, what is ATP in week 5
A. 10
B. 0
C. 30
D. 20